Aquatic center, "Les grands bains"

Herblay (95), France

MAITRISE D’OUVRAGE
Parisis’s township committee

REALIZATION 2014

CONSTRUCTION COST
€13,2 M VAT

PROGRAM
Sports pool: 25x15m
Leisure pool: 180m²
Activity pool: 120m²
Recreational area for children: 50m²
Wellness area: 320m²

Surface area : 3 500m²

PROJECT MANAGEMENT
Lead architect: Jacques Rougerie
Scenographer: agence 2a
Engineers for fluid: ethis
Structural engineers & economics: CET ingenierie
Acoustic engineers: Peutz et Associés
Landscaper: Alice Tricon

DESCRIPTION
The project is defined by the integration of the vegetal environment of the maple tree through the architectural elements composing the project present in: the volumes, the openings, the dynamic lines, the materials, the colours. A revealing architectural work, carefully presented, Original and contemporary, with shapes sometimes inspired by the leaf, trunk and fruit of the Maple tree, for an entrance to the new green district.